Site evaluation meeting at Friendly House

Attendees:
James Schementi
Gary Pollice
Jerry Schlater

Summary:
Initially we discussed the issue that I still did not have access to the baseline ETO Software. Also, it was pointed out that the internet connection on site was inconsistantly up and unsatisfactory for using an online system.

After inspecting their current physical infastructure, we concluded to shift the focus of the project initially to upgrading and replacing their physical LAN infastructure and then take it from there.